Project schedule

The steps to your labelling machine

Discussion of your requirements, production conditions and labelling guidelines

You describe your requirements and wishes for your labelling system to us. Your production conditions and production environment also play an essential role in the quotation. Our experts and specialists are available to answer your questions or discuss open issues regarding the implementation of EU directives or global labelling requirements. In the best case, we will have product and label samples as well as a labelled product from a customer even before the quotation is prepared. If you provide us with a technical specification, we will check this accordingly and take the requirements into account when preparing the offer.

 

Our sales staff will send you a technical questionnaire even before the offer is prepared. This was developed by our committee - consisting of our technical and commercial experts - in order to clarify essential questions in advance and to be able to provide you with an offer that is as concrete as possible. If you have any further questions regarding our technical questionnaire, our experts will be happy to assist you.

 

Do you still have any internal open points regarding your requirements? We would be pleased to submit you a budget offer or an indicative offer first.

Unbenannt-1.png

Quotation and order

Once all requirements, production conditions and guidelines have been clarified, we will work out a solution concept for you and prepare a detailed offer. If you have any questions or requests for changes to the quotation, our sales team is available to you at any time.  Your order can be placed on the basis of the quptation.

Unbenannt-3.png

Project management

Depending on project size, requirements and agreement, we will provide you with a project manager. After your order, he will clarify with you the scheduling of corresponding milestones such as the sending of your product samples, the release of the design drawing, FAT and commissioning. The project manager will monitor the time schedule. The project manager is available to you throughout all phases of the project to answer your questions and to clarify open points. 

Unbenannt-4.png

Design and approval

The design of your labelling machine is carried out in consultation with you. You will then receive an approval drawing from us. After receiving your approval, our design team will begin with the detailed design of your labelling machine. The detailed planning concludes with the preparation of parts lists and material procurement.

Unbenannt-2.png

Assembly and internal acceptance

Through our supply chain management we ensure that the required materials are in house in time. Then the mechanical and electrical assembly of the labelling system can take place. The internal acceptance serves as a preliminary test. During the internal acceptance test runs of the system with your label and product combinations are carried out. After the internal acceptance test, we will arrange an appointment with you for a FAT.

FAT and commissioning at customer site

The FAT takes place at our premises. This is where we again carry out test runs and performance tests of the plant together with you on the basis of the qualification documents. Afterwards, the system is delivered and the labelling machine is commissioned and integrated into your production line or packaging line.